Duration for Removal of formwork
As a Site Engineer or supervisor it’s important for carrying out the project in a good manner.
S.NO. | STRUCTURAL MEMBERS | DURATION |
1. | Slabs( when props left under) | 3 days |
Removal of props to slabs of spanning upto 4.5m | 7 days | |
Removal of props to slabs of spanning over 4.5m | 14 days | |
2. | Beam soffits (props left under) | 7 days |
Removal of props to beams of spanning upto 6m | 14 days | |
Removal of props to beams of spanning over 6m | 21 days | |
3. | Columns and vertical sides of beams and walls | 1 to 2 days |