Duration for Removal of formwork

As a Site Engineer or supervisor it’s important for carrying out the project in a good manner.

S.NO.STRUCTURAL MEMBERSDURATION
1.Slabs( when props left under)3 days
Removal of props to slabs of spanning upto 4.5m7 days
Removal of props to slabs of spanning over 4.5m14 days
2.Beam soffits (props left under)7 days
Removal of props to beams of spanning upto 6m14 days
Removal of props to beams of spanning over 6m21 days
3.Columns and vertical sides of beams and walls1 to 2 days