For wall column and vertical faces of all the structural members, the form work is generally removed after

QuestionsCategory: Civil EngineeringFor wall column and vertical faces of all the structural members, the form work is generally removed after
VideRime Staff asked 3 years ago

For wall column and vertical faces of all the structural members, the form work is generally removed after

a) After 24 to 48 hours   (Ans)

b) After 3 days

c) After 7 days

d) After 14 days