Consider the following statements in a situation where cement and steel are supplied by the department. I: 10% profit should be added on the cost of cement and steel. II: Cost of carriage from godown to site work should be added. Which of the following options is true?
Questions › Category: Civil Engineering › Consider the following statements in a situation where cement and steel are supplied by the department. I: 10% profit should be added on the cost of cement and steel. II: Cost of carriage from godown to site work should be added. Which of the following options is true?
Consider the following statements in a situation where cement and steel are supplied by the department.
I: 10% profit should be added on the cost of cement and steel.
II: Cost of carriage from godown to site work should be added. Which of the following options is true?
1. Only statement I is true
2. Both statements I and II are false
3. Both statements I and II are true
4. Only statement II is true (Ans)